DTI

Goulburn River Solar Farm

Delivering renewable energy to Australia’s grid.

Goulburn River Solar Farm project, NSW
Location
Merriwa, NSW
Sector
Energy & Renewables
Client
Lightsource bp
Timeline
Commenced 2025

The Goulburn River Solar Farm is a signature renewable energy project located in the Upper Hunter Region of New South Wales. This 585 megawatt-peak solar farm will generate approximately 1.3 million megawatt-hours (MWh) of renewable energy annually to power around 225,000 homes.

Currently under construction, this monumental project encompasses the construction of a 558MWdc capacity solar farm and a 49 MW/562 MWh Battery Energy Storage System (BESS), aimed at enhancing grid reliability and optimising energy distribution.

Delivered for Lightsource bp, DT Infrastructure is undertaking a comprehensive scope of works including civil, structural, and electrical infrastructure to install one million bifacial panels and 112 individual battery units to the grid.

When operational, the solar farm is expected to reduce carbon emissions by 910,000 tonnes annually, a significant step in decarbonising our economy and realising our goal of a clean energy future.

Scope
  • Installation of approximately one million bifacial solar panels on solar trackers, continually orienting them towards the sun.
  • Civil works for major upgrades to existing roads and internal access roads.
  • Development of electrical infrastructure to integrate the facility with the existing grid.
  • Construction of 49 MW/562 MWh Battery Energy Storage System (BESS) comprised of 112 individual battery units.
  • Construction of an additional transmission tower within the existing easement to connect the Goulburn River Solar Farm to the electricity network.
  • Installation of fencing and site protection infrastructure.
  • Development of a high-voltage substation bench, crucial for stepping up medium voltage from solar inverters to transmission levels, expanding the solar farm’s distribution capabilities.

225,000

Generating renewable energy to power approximately 225,000 homes annually.

910,000

A goal to reduce carbon emissions by approximately 910,000 tonnes annually.

1,000,000

Installing 1 million bifacial panels

112

Construction of 49 MW/562 MWh Battery Energy Storage System (BESS) comprised of 112 individual battery units.

1,200

Delivering Lightsource bp’s biodiversity stewardship which will span 1,200 hectares.

350

Creating 350 construction roles throughout the life of the project.

Social impact
  • Generating enough renewable energy to power approximately 225,000 homes annually.
  • A goal to reduce carbon emissions by about 910,000 tonnes annually.
  • Creating 350 construction roles throughout the life of the project.
  • Delivering Lightsource bp’s biodiversity stewardship scheme which will span 1,200 hectares, ensuring the preservation of native vegetation in perpetuity.
  • Building strong relationships with the Wanaruah Land Council to support and care for Country and First Nations cultural heritage.

Renewables News

Renewables Projects

Deliverables
  • Modernising Transperth’s signalling and train control technology to a digital solution, with upgrades to signalling along the total length of track on the Transperth network.
  • Installation of more than 7,000 transponders enabling precise train location.
  • In-cab signalling equipment for 125 trains including the Prospector, AvonLink and Australind regional trains.
  • Improved passenger information with more than 600 displays at 87 stations across the network.
  • ⁠Installation of more than 250km of electrical conduit.